Skip to main content
Skip to sub-navigation
About USAID Our Work Locations Policy Press Business Careers Stripes Graphic USAID Home
USAID: From The American People Telling our Story Spring water is distributed through a new pipe system - Click to read this story
Telling Our Story
Home »
Submit a story »
Calendars »
FAQs »
About »
Stories by Region
Asia »
Europe & and Eurasia »
Latin America & the Carribean »
Middle East »
Sub-Saharan Africa »

 

Egypt
USAID Information: External Links:

Philippines - Nonita de la Peña in her Mindinao electrical store   ...  Click for more stories...
Click for more stories
from Asia and the Near East  
Search
Search by topic or keyword
Advanced Search

 

Aswan High Dam Gets Modern Controls
Challenge

Spanning the Nile River with twelve hydroelectric turbines that can generate 2.10 million kilowatts of electrical power, the Aswan High Dam Power Station remains Egypt’s largest single source of energy. But by the 1990’s, the instruments and controls that monitor the performance of the turbines and all station facilities had become obsolete since installation in the 1960’s.

Initiative

After Egypt’s Ministry of Electricity determined that key equipment in the station needed to be repaired or replaced, the U.S. Agency for International Development was asked to provide assistance. In the early 1980’s, an agreement was signed with the Government of Egypt for the rehabilitation and modernization of the High Dam power station.

Most recently, USAID provided $13.5 million to help the Egyptians install a state-of-the-art control system at the Aswan High Dam. USAID funded $154 million in improvements to the High Dam since the late 1980’s including six major upgrades which have replaced or rehabilitated the vital components of the station. Besides the physical improvements to the station, more than 100 operations and maintenance staff received comprehensive training at manufacturers’ factories in the United States.


Photo:Control system at the Aswan High Dam
Photo: USAID/Egypt

Control system at the Aswan High Dam

Results

After a three-year replacement project, the power station is now run with microprocessor-based controls and data acquisition systems that let maintenance personnel identify and prevent potential problems. Circuit breakers were replaced, as well as the controls and instrumentation that both regulates and monitors the transfer of power from the generation station to the 500 KV transmission lines.

The completed facilities were dedicated in September 2003. The efficiency of the station has been improved and the life of the plant has been extended by more than 30 years. The projects have increased generator performance, overall station safety, and efficiency, and therefore service to the Egyptian public.

Print-friendly version of this page (248kb - PDF)

Back to Top ^

 Digg this page : Share this page on StumbleUpon : Post This Page to Del.icio.us : Save this page to Reddit : Save this page to Yahoo MyWeb : Share this page on Facebook : Save this page to Newsvine : Save this page to Google Bookmarks : Save this page to Mixx : Save this page to Technorati : USAID RSS Feeds Star